All residents of the Gardens, Meadows, Manors and Kensington sub-associations will be receiving a copy of this letter from Adams Landscaping that explains the type of work that will be performed and asks for our cooperation while the new lawn gets established. The costs for these improvements are being funded by the developer, not the Central Park Master Association. Upon completion, the Master Association will become responsible for the costs to maintain these improvements.
Here is Adams Landscaping's timetable for this project:
- Install Meter – completed
- Repair irrigation – completed 09/21
- Complete vegetation kill – completed 09/22
- Distribute homeowner letters – completed by 09/25
- Begin grading operations, topsoil, seeding – starting the week of 10/05
- Finish complete project by 10/20