Wednesday, May 19, 2010

Exterior Painting

Our exterior painting contractor began work this past Monday. Their first step is to identify, remove and replace all deteriorated wooden trim. These trim pieces have been marked with an orange paint stripe and they will be returning to remove them and install new trim pieces, which will then be painted with a primer before work begins on repainting the exterior of the affected units.

Removal and replacement of the deteriorated trim is a noisy task. Please bear with us while this vital work is performed.

The first 46 Units on this list will be painted this summer. The contractor will decide the actual order in which they will be completed. The contractor will return next year to work on the 47th through 105th Units on that list.