Last Updated on Aug. 3rd:
The seal coating portion of this project is now complete. The only remaining work to be performed is the striping of the pedestrian crosswalks, which will not require any street closures or parking inconveniences. Thank you for your cooperation.
The seal coating portion of this project is now complete. The only remaining work to be performed is the striping of the pedestrian crosswalks, which will not require any street closures or parking inconveniences. Thank you for your cooperation.
The Central Park Master Association is having a seal coat applied to the asphalt road surfaces of North, East, South and West Central Park Avenues during the week of July 16, 2012. Sections of these roads and intersections will be closed while the work is performed. This work does not include the Manors private access drives that are parallel with North Central Park. On certain days the Van Dyke entrance to Central Park will be closed and on other days, the 22 Mile Rd. entrance will be closed. It will take six Work Days to complete this project.
Here is the full project plan along with an updated map, scheduled Work Days and locations of the road closures. A hard copy of the original plan was delivered to each home prior to Monday, July 16th.
If rain is forecast, the contractor will cancel that Work Day and move it to the next scheduled date, with the remaining schedule delayed accordingly. Below is the latest Work Day schedule, which was revised to add Work Day 6 (to do the northerly portion of what had been planned for Work Day 2). Check back here regularly to see the latest schedule.
- Work Day 1 was completed on Monday, July 16, 2012.
- Work Day 2 was completed on Friday, July 20th
- Work Day 3 was completed on Wednesday, July 25th
- Work Day 4 was completed on Monday, July 30th - everyone must enter and leave via Van Dyke
- No seal coat work planned for Tuesday to avoid interference with the trash collection.
- Work Day 5 was completed on Wednesday, August 1st - everyone must enter and leave via 22 Mile Rd.
- Work Day 6 was completed on Thursday, August 2nd.